Are there any limitations on the number of lines within a program?


Forum|alt.badge.img
  • Bronze Active Participant
  • 1 reply

Hi All,

Does anyone have any idea on any limitations on the number of lines within a program, and how long it takes to open a a Program with 2-3k lines?

Thanks in advance

Haydn

2 replies

Limori
Planview Falcons
Forum|alt.badge.img+4
  • Planview Falcons
  • 75 replies
  • March 21, 2024

Hi Haydn

There is no driven limitation of lines within a program or project.

You do need however to consider the bigger the work plan hierarchy structure, the longer it might take to load.

Please do be mindful that loading time would also depend on the number of columns that are you are displaying in your view.


Forum|alt.badge.img
  • Author
  • Bronze Active Participant
  • 1 reply
  • March 21, 2024

Thanks Limor…. and understand the variables, so to further clarify I wouild like to get understanding of is an acceptable timeframe for a 3k line Program to load in the ‘plan’ view, using a cloulmn set with 15 attributes (noncalculated) to load, assuning an internat commection => 50 mbps:

05 to 10 seconds?

10 to 30 seconds?

30 to 60 seconds?

60  seconds+?

Thanks in advance.

Haydn