Crosstab Week Reporting Date Formatting

  • March 13, 2024
  • 2 replies
  • 78 views

Forum|alt.badge.img+3

Hello,

 

I have a weekly crosstab report that shows the week’s data but with headers of W-01, W-02, etc. which can get a bit confusing when looking at weekly data.

 

Wondering if anyone has knowledge of if/how to set it so it actually show’s the week date?

 

Thank you!

Best answer by Aayush

Hi @kayla.schwarz 

As you've raised a support case on the same, we would recommend hovering on the column will show the date range of the week. 

 

This topic has been closed for replies.

2 replies

Aayush
Planview Falcons
Forum|alt.badge.img+4
  • Community Manager
  • March 19, 2024

Hi @kayla.schwarz This is indeed a valid use case. Thank you for bringing up this question within the community. I will discuss it with my product team to explore potential workarounds and report back here. 


Aayush
Planview Falcons
Forum|alt.badge.img+4
  • Community Manager
  • Answer
  • March 20, 2024

Hi @kayla.schwarz 

As you've raised a support case on the same, we would recommend hovering on the column will show the date range of the week.