Hi all
In our Baseline View we show:
- Baseline days and £s - project lifetime
- Allocated days and £s - project lifetime
- Actual days and £s - (obviously) to date
Is there a column view that can be added to show our PMs:
- Baseline days and £s - to date
- Allocated days and £s - to date