We have projects that could have more than 200 activities.

At the time the project manager has to add the user per activity; is there a way to add a user to multiple activities in a rapidly way?.

 

 

 

In AdaptiveWork, you can copy and paste resources to create the link between a User and Work Item. I’m not sure if this functionality exists in PPM Pro. You can also use the Data Loader to do a mass batch upload and create the link too, but it’s a little more complex than copy and paste.