In the Resource Load - Where does the Capacity value for a resource come from?

  • March 19, 2025
  • 1 reply
  • 27 views

Forum|alt.badge.img

In the Resource Load - Where does the Capacity value for a resource come from.  I have a resource that has 5.33 days capacity a week, when it should be 5 days.  The resources calendar has not been edited.

Thanks in advance :)

This topic has been closed for replies.

1 reply

Aayush
Planview Falcons
Forum|alt.badge.img+4
  • Community Manager
  • April 14, 2025

Hello Bina - Thanks for flagging this! Since your case was a bit unique, it was a great call to open a support ticket. I see that the case has now been resolved—glad to hear it!