Question

Is it possible to have multiple milestones active within a project at a time?

  • June 14, 2024
  • 1 reply
  • 30 views

Forum|alt.badge.img+1

I want to keep multiple milestones active at same time. Has anyone tried?

This topic has been closed for replies.

1 reply

Nathan Hare
Planview Partner
Forum|alt.badge.img
  • Planview Partner
  • June 14, 2024

Hi Deepti,

Yes! You can certainly have multiple milestones active at one time. One consideration is that the sub-items will follow the parents state. For example, if you have three milestones under a project that are all active and you update the project state to completed, on-hold, cancelled, draft, or requested. All of the milestones under the project will follow the state that you select.