Skip to main content

Hello community,

We hope everyone is doing well.

We have a concern regarding a situation that arises when importing schedules from MS Project to Adaptive Work.

In PV Portfolios, it is possible to import a project schedule from MS Project while specifying how it should be imported. This allows us to avoid relationships between predecessor and successor activities, restrictions, flags, and resource assignments.

We would like to know if there is a similar functionality in Adaptive Work to prevent dates from appearing as “user-defined” when importing from MS Project. We require this because having date restrictions prevents the system from automatically calculating durations and dates. Consequently, we need to manually remove each restriction to enable proper planning.

¿How do you usually handle this issue with the restrictions in Adaptive Work?
 

Best regards,

Oscar Suarez

Hello Oscar - We would recommend you reaching out to Planview support on this. This is a very valid use-case and our support team could look into this and provide the best alternative. 


Reply