Skip to main content
Question

Ms Project Importing in AdaptiveWork without restrictions

  • 18 June 2024
  • 0 replies
  • 45 views

Hello community,

We hope everyone is doing well.

We have a concern regarding a situation that arises when importing schedules from MS Project to Adaptive Work.

In PV Portfolios, it is possible to import a project schedule from MS Project while specifying how it should be imported. This allows us to avoid relationships between predecessor and successor activities, restrictions, flags, and resource assignments.

We would like to know if there is a similar functionality in Adaptive Work to prevent dates from appearing as “user-defined” when importing from MS Project. We require this because having date restrictions prevents the system from automatically calculating durations and dates. Consequently, we need to manually remove each restriction to enable proper planning.

¿How do you usually handle this issue with the restrictions in Adaptive Work?
 

Best regards,

Oscar Suarez

Be the first to reply!

Reply