Do task assignments take into consideration the remaining effort, and if not, how to best handle this?
Example: New task created starting today, with 100 hours of Work, and duration of 2 months. This equals 12.5 hours of work per week.
- This task gets marked as 50% complete on day 1, which signals that 50 hours of Work are remaining, or 6.25 hours of task assignment effort per week.
- From what I can see, the Task Assignment will still show 12.5 hours despite the progress suggesting otherwise.
Does AdaptiveWork consider Remaining Work as part of the Task Assignment numbers for future days of an open task’s schedule?
Perhaps I am misunderstanding a feature that already exists, or the way it is meant to work.
Any insights or information on this would be greatly appreciated.