Hello! My team has been playing around with capacity planner lately and found that as a resourcing manager, you’re able to make changes to a resource's demand manually in the planner and then submit. This seems to update the capacity planner without making changes to the project, which is good since able to be we want to forecast what is the real projected demand per resources which might not be reflected in the project plan. 

The problem is that it seems that once you submit, these hours seem to disappear from the capacity planner by the next day. Is this a normal behavior from the planner?

 

Found a solution …. it had to do with a schedule workflow rule that would set task assignments at the project level. After disabling this to test, we verified that the modified amounts added to the capacity sheet did not change overnight. 