Skip to main content
Solved

Working days vs Calendar days on Lag Duration Import (DependencyLinks)

  • July 25, 2025
  • 5 replies
  • 95 views

Forum|alt.badge.img+1
  • Gold Active Participant

I am importing a project WBS and I am building a data loader import to capture the predecessor information for each workitem as a DependencyLinks import.

 

In the source data, some of the Lag durations are in workdays (d) and some are in calendar days (ed). ed basically includes weekends, holidays, etc. 

 

Is there a way to indicate the difference between these two duration types for my import?

Best answer by Shana

Thank you for following up. I have been meaning to post my successful results. Turns out, ‘ed’ is not how you do it. Its ‘cd’. Here is an example of a dependencylink data load sheet that worked for me. Make sure you verify which is the ‘WorkItem’ and which is the ‘DependsOn’, because I originally had it switched around. 

 

DependsOn WorkItem DependencyType Lag
T-80602 T-80610 FTS 1d
T-80602 T-80611 FTS -1d
T-80602 T-80621 FTS 0d
T-80603 T-80602 FTS 120cd
T-80649 T-80602 FTS 10cd
This topic has been closed for replies.

5 replies

Forum|alt.badge.img+2
  • Planview Falcons
  • July 30, 2025

@Shana 
 

When you're importing lag durations in AdaptiveWork, here's how to make sure they’re set correctly depending on whether you want to count workdays or calendar days:

To control how the lag is calculated, include the Duration Type in your import file:

  • Choose "Default" if the lag should count only working days (skipping weekends and holidays)

  • Choose "Consecutive" if the lag should count all calendar days (including weekends and holidays)

For example:

  • If you want 5 workdays of lag: Lag = "5d", Duration Type = "Default"

  • If you want 5 calendar days of lag: Lag = "5d", Duration Type = "Consecutive"

Just make sure both the Lag and Duration Type fields are included in your file so the system can apply it correctly.


Forum|alt.badge.img+1
  • Author
  • Gold Active Participant
  • July 30, 2025

The Entity DependencyLink does not include a field called “Duration Type” (Metadata Explorer), and when I upload a file, I get this error on that column: 

Field 'Duration Type' not found in the entity 'DependencyLink', the entire column will be ignored

 

Where do I import the ‘Duration Type’ information?

 

 

Also, when I import Lag in the form of, say, ‘120ed’, the Data Loader reads that as ‘120 Days OverrideEnd’. What is that about?

 

Thanks for your response. 


Forum|alt.badge.img+2
  • Planview Falcons
  • August 13, 2025

You're correct that the lag type is specified directly in the duration format since there's no separate "Duration Type" field in the DependencyLink entity:

Standard Format:

  • 5d = 5 working days (business days only)
  • 5ed = 5 elapsed days (calendar days including weekends/holidays)

The error 120 Days OverrideEnd suggests the Data Loader may not be properly interpreting the 120ed format, which could be due to several factors:

Quick Test: Before diving deeper, try importing a single dependency with a smaller elapsed day value like 5ed to confirm whether this is a format issue or something specific to the larger 120-day duration.

If the test fails: This appears to be a system-specific Data Loader issue that would benefit from direct review. I'd recommend opening a support ticket with:

  • Your import file sample
  • The exact error message
  • Your current field mappings

The support team can examine your specific environment and file structure to identify whether this is a format limitation, validation rule, or configuration issue.

If the smaller test works: There may be validation limits on lag duration values that need to be addressed through your system settings.

 


Forum|alt.badge.img+1
  • Author
  • Gold Active Participant
  • Answer
  • August 13, 2025

Thank you for following up. I have been meaning to post my successful results. Turns out, ‘ed’ is not how you do it. Its ‘cd’. Here is an example of a dependencylink data load sheet that worked for me. Make sure you verify which is the ‘WorkItem’ and which is the ‘DependsOn’, because I originally had it switched around. 

 

DependsOn WorkItem DependencyType Lag
T-80602 T-80610 FTS 1d
T-80602 T-80611 FTS -1d
T-80602 T-80621 FTS 0d
T-80603 T-80602 FTS 120cd
T-80649 T-80602 FTS 10cd

Forum|alt.badge.img+2
  • Planview Falcons
  • August 13, 2025

Thank you for sharing your solution and the helpful tip on verifying the ‘WorkItem’ and ‘DependsOn’ fields.