We expect that projects with "Respect Durations" setting on will push effort that is not tracked against to the future.
BUT this doesn't seem to be working in the system - why?
We a ticket several days ago to Customer Support asking WHY the "Progress Tasks and Allocations" has the “Respect Durations” option selected for projects BUT it is not moving the allocation end date forward, the effort is just piling up against the date.
Is it because we aren't using requested start date? Do we need to import that date for every project?
Separate issue: WHY are % utilization going over 300%? We have made that the max