Prevent Resource Manager from Over Allocating to Requirement

  • April 6, 2026
  • 1 reply
  • 38 views

rzb1qs
Silver Innovator
Forum|alt.badge.img+1

We utilize Demand Managers to input Requirements into Projects.  Those requirements are “Assigned To” a Resource Manager / Supervisor.  Is there a way to prevent that Supervisor from “Over Allocating” to that requirement?  We see this when a Supervisor needs to “fill time” for one of their employees, and the often do this by Allocating that employee more that the project requirement needs.  

This topic has been closed for replies.

1 reply

Forum|alt.badge.img+1
  • Silver Active Participant
  • April 21, 2026

There is no option that I know of to prevent this. Basically RM’s own the allocations for their resources. If they think it will take 60 hrs instead of 40, they can make it 60.