Prevent Resource Manager from Over Allocating to Requirement

  • April 6, 2026
  • 1 reply
  • 21 views

rzb1qs
Silver Innovator
Forum|alt.badge.img+1

We utilize Demand Managers to input Requirements into Projects.  Those requirements are “Assigned To” a Resource Manager / Supervisor.  Is there a way to prevent that Supervisor from “Over Allocating” to that requirement?  We see this when a Supervisor needs to “fill time” for one of their employees, and the often do this by Allocating that employee more that the project requirement needs.  

1 reply

Forum|alt.badge.img
  • Silver Active Participant
  • April 21, 2026

There is no option that I know of to prevent this. Basically RM’s own the allocations for their resources. If they think it will take 60 hrs instead of 40, they can make it 60.