Primary Work Structure - Work Breakdown Structure View

  • Oct 16, 2025 12:46 PM UTC
  • 2 replies
  • 202 views

Forum|alt.badge.img
  • Bronze Active Participant

In a previous version of Planview Portfolios, we could open a Work entity and simply click the “expand” arrow beside the Work Breakdown Structure section in the Work Detail tile to see where the entity was located within the primary work structure:

Work Detail Tile - Work Breakdown Structure section expanded

In the latest version of Planview Portfolios, I’m trying to find that same information while in Work View. When I asked my administrator, they suggested a workaround: navigate to Work > Show All Work, search for the specific work item, and then click the hierarchy icon to view the full WBS path.

This method works, but it requires several extra steps compared to the previous version, where the information was readily accessible with a single click.

Is there a more efficient way to view the WBS location of a work entity in the current version?

Best answer by pamela.sargent

​@TracyC - in our work detail screen we replicated this visibility by adding each work hierarchy level as an attribute on the work detail screen.  The admin would find these by the name they call each level with the last level (level above project name) called Parent Description.  Below is an example but the labels are probably different for your org. 

 

Best regards,

Pam Sargent
NASCO

View original
This topic has been closed for replies.

2 replies

pamela.sargent
Platinum Knowledge Guru
Forum|alt.badge.img+7
  • Platinum Knowledge Guru
  • Answer
  • Oct 16, 2025 12:56 PM UTC

​@TracyC - in our work detail screen we replicated this visibility by adding each work hierarchy level as an attribute on the work detail screen.  The admin would find these by the name they call each level with the last level (level above project name) called Parent Description.  Below is an example but the labels are probably different for your org. 

 

Best regards,

Pam Sargent
NASCO


Forum|alt.badge.img
  • Author
  • Bronze Active Participant
  • Oct 30, 2025 2:11 PM UTC

​@TracyC - in our work detail screen we replicated this visibility by adding each work hierarchy level as an attribute on the work detail screen.  The admin would find these by the name they call each level with the last level (level above project name) called Parent Description.  Below is an example but the labels are probably different for your org. 

 

Best regards,

Pam Sargent
NASCO

This is exactly the tip we needed and what we were looking for.  When I shared this with our administrators, they were able to mimic your suggestion.  Thanks for taking the time to answer!