It’s not very common, but we have some team members whose available capacity varies by quarter. Just like there’s an ability to contour allocations, is there a way to contour available capacity multiplier?

If not, does anyone have a reasonable alternative?

TIA!

Best answer by Yathy

Hi @ndurgampudi Thats a good thought, but I don’t think currently PPM Pro have something similar to contour allocation on capacity multiplier. But I think you can make use of calendar events to tackle this variation in available capacity of resources. Since this is not so common and I am assuming this might be for very less number of resources, you can create a new calendar with all unavailable dates or hours and then allocate that calendar to the resources. 

 

Would like to hear from others also, if you have any workaround for this scenario.

 

View original
Did this topic help you find an answer to your question?

1 reply

Yathy
Planview Falcons
Forum|alt.badge.img
  • Planview Falcons
  • 7 replies
  • Answer
  • April 1, 2024

Hi @ndurgampudi Thats a good thought, but I don’t think currently PPM Pro have something similar to contour allocation on capacity multiplier. But I think you can make use of calendar events to tackle this variation in available capacity of resources. Since this is not so common and I am assuming this might be for very less number of resources, you can create a new calendar with all unavailable dates or hours and then allocate that calendar to the resources. 

 

Would like to hear from others also, if you have any workaround for this scenario.

 


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings